The Energy Act 2011 included provisions for the 'Green Deal', a Department of Energy and Climate Change (DECC) initiative offering a mechanism for funding energy efficiency improvements. Instead of paying up-front to have energy efficiency measures installed in a property, the cost was funded by long-term savings on electricity bills. The Green Deal was launched in autumn 2012, but financing did not become available until January 2013.
Under the scheme, a 'green deal provider' financed the up-front costs, and the consumer's energy supplier added a 'green deal charge' to the consumer’s bill. The 'golden rule' was that this charge must be less than (or at least no more than) the savings in the consumers bill resulting from the energy efficient measures installed. As a consequence, the consumer’s overall bill should be the same, or lower than it was before the energy efficiency measures were installed.
The Green Deal charge was ‘attached’ to the meter, so if the property was sold, the purchaser took on the charge. The deal remained with the meter even if the energy supplier changed.
To obtain energy efficiency measures through the Green Deal, consumers first arranged for an assessment by an accredited green deal assessor (this might be arranged by a green deal provider). They carried out an assessment of the property and the way it was used, then proposed a package of energy efficiency measures for the property and predicted the likely energy savings that would result.
A green deal provider would then offer a green deal plan to the consumer, outlining the energy efficient measures that they would finance and the resulting green deal payment that would be added to their future energy bills. If the consumer agreed, an accredited installer would implement the measures. The consumers energy supplier would then add a green deal charge to their energy bill.
The range of energy efficiency measures that might qualify under the Green Deal included:
- Loft insulation.
- Solid wall insulation.
- Cavity wall insulation.
- Draught insulation.
- Double glazing.
- Wind turbines.
- Water-source heat pumps.
- Air-source heat pumps.
- Ground-source heat pumps.
- Solar blinds, shutters and shading devices.
- Door insulation.
- Smart meters.
- Thermal and photo voltaic panels.
- Biomass boilers.
- Controls for heating ventilation and air-conditioning.
- Radiant heating.
The pay-back period for domestic properties could not exceed the length of time the improvements lasted. For non-domestic properties, the pay-back period could be shorter, to allow payback within the lease period. This was because, unlike the domestic sector, energy use may vary significantly between successive users of a non-domestic property.
[edit] Green Deal Home Improvement Fund
In June 2014, the Green Deal was supplemented by a Green Deal Home Improvement Fund (GDHIF). The Green Deal Home Improvement Fund provided up to £7,600 for domestic energy customers and was designed to work alongside Green Deal finance although householders were not required to use Green Deal finance to qualify for the GDHIF. See Green Deal Home Improvement Fund for more information.
[edit] Issues
Some critics suggested that the calculations underpinning predicted savings were too optimistic. To predict savings, costs had to be estimated, and these are dependent not only on the use of the property, but also the long-term price of energy and the details of the specific tariff the consumer signs up to. The Department of Energy and Climate Change itself said that...
'….actual cash savings cannot be guaranteed by government since no-one except individuals and businesses themselves can control how much energy they actually consume in their own property.'
(Ref. DECC, The Green Deal: A summary of the governments proposals.)
Other issues included:
- The interest rate that green deal providers charged for financing (perhaps 6-10%), and whether householders would be better to finance improvements themselves.
- Concerns about whether the Green Deal would simply allow expensive energy efficiency measures to be installed on properties that were already fairly efficient, whilst not being taken up on properties where very simple and low-cost measures had yet to be installed.
- The quality and cost of assessors.
- The quality of installers.
- Concerns about the applicability of assessment and retrofitting techniques to some of the UK's 'traditional' building stock (pre 1919), which behave differently in relation to ventilation and moisture than more modern buildings. Ref Responsible Retrofit of Traditional Buildings, the Sustainable Traditional Buildings Alliance.
In September 2014, the Energy and Climate Change Committee published Energy and Climate Change - Third Report The Green Deal: watching brief (part 2). This criticised the Green Deal, proposing that, '... the Government must re-evaluate its approach and set out a clear strategy to revive the failing scheme. Unless the package is made more attractive to a wider group of consumers, Green Deal finance is likely to remain unappealing to many.'
[edit] Cancellation
On 23 July 2015, then-Climate Change Secretary Amber Rudd announced that there would be no further funding to the Green Deal Finance Company and that the Government would stop any future funding releases of the Green Deal Home Improvement Fund. This was described as a move to protect taxpayers following low take-up and concerns about industry standards. (Ref. Gov.uk.) The announcement did not impact on existing Green Deal Finance Plans or Green Deal Home Improvement Fund applications or vouchers.
The Framework to support the programme, remains in place to service existing Green Deal Plans and for any private finance providers wishing to enter the market.
Rudd suggested that the Government would work with the building industry and consumer groups on a new value-for-money approach, but that future schemes must provide better value for money, supporting the goal of insulating a million more homes over the next five years and the Government’s commitment to tackle fuel poverty.
See Green Deal scrapped for more information.
On 14 April 2016, the National Audit Office (NAO) published Green Deal and Energy Company Obligation, in which it concluded that the Green Deal had not achieved value for money, had cost taxpayers £240 million and had not generated additional energy savings. This, it suggested, was because the Department of Energy and Climate Change (DECC) had not persuaded householders that energy efficiency measures were worth paying for.
[edit] Reform
In October 2017, a Call for Evidence was published alongside the Government’s Clean Growth Strategy. The call for evidence is intended to improve knowledge of stakeholders’ views on the Green Deal Framework and whether there is scope for changing it to better support needs.
[edit] Related articles on Designing Buildings Wiki
- Active House.
- Air source heat pumps.
- Climate change science.
- Domestic micro-generation.
- EIT Climate-KIC.
- Emission rates.
- Energy Act.
- Energy certificates.
- Energy company obligation.
- Energy performance contracts.
- Energy targets.
- Feed in tariff.
- Green building.
- Green Deal Consultation.
- Green Deal Home Improvement Fund.
- Green Deal scrapped.
- ISBEM
- NAO report into the Green Deal and Energy Company Obligation.
- Renewable energy.
- Renewable heat incentive.
- Simple payback.
- Sustainability.
- The Government's 10-point plan: what's missing?
- Zero carbon homes.
- Zero carbon non domestic buildings.
[edit] External references
- Gov.uk Green Deal.
- DECC, The Green Deal: A summary of the governments proposals.
- Responsible Retrofit of Traditional Buildings, the Sustainable Traditional Buildings Alliance.
- The Energy Act 2011
- BRE: The green deal.
- Statement from Energy and Climate Change Minister Greg Barker on the latest Green Deal statistics. 11 April 2013
Featured articles and news
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.